Building the New National Library of Israel Complex

The new NLI building, adjacent to the Knesset and the Israel Museum at the intersection of Kaplan Street and Ruppin Boulevard in Jerusalem's National District, is being planned by Swiss architecture firm Herzog & de Meuron.
The building's area totals approximately 45,000 sq. m. including 6 above-ground floors comprising 15,000 sq. m., and 5 below-ground floors totaling 30,000 sq. m.
 

Updates on Construction

 

 
July-August 2019
   
 
We have now completed the concrete framework (floors, walls and ceilings) up to floor B1 (the fifth floor from the bottom of the building, one floor below ground level). The work is moving ahead promptly and will be followed by continued construction upward. Completion of heating, ventilation, and air conditioning (HVAC), electrical and plumbing systems in all subterranean levels is now also being completed alongside all other necessary infrastructure work. 
 
The new building's most groundbreaking sustainability feature will be Israel's first below-ground "rock store", a mechanism for storing thermal energy which will significantly reduce energy consumption required to cool the building. The concrete foundations for the 'rock store' sustainable cooling system have been cast, and all of the stones have been placed in the enclosures.
 

April 2019

   

January 2019

   

October 2018

   

August 2018: Work begins on building foundations

Following the completion of excavations at the site, work has now been passed on to Electra Construction Ltd., who have already begun casting concrete for the new building's foundations

   

May 2018: The digging and reinforcement work is complete
The excavation and retaining wall work has been completed.
The five subterranean floors of the new building have been fully excavated with over 200,000 cubic meters (ca. 7,000,000 cubic feet) of earth removed from the site.

   

A 40 sq. m. (ca. 430 sq. ft.) mock-up of a corner of the building has been erected on site. It serves to demonstrate what the façade will look like and will help the planning team and staff better examine and optimize various aspects of project implementation moving forward

Click to watch >>


 

Excavations & Retaining Walls, October 2016 status report (click to watch)


Excavations & Retaining Walls, September 2016 status report (click to watch)


Excavations & Retaining Walls, July-August 2016​


 


Excavations & Retaining Walls June 2016 (click for report)


Excavations & Retaining Walls May 2016 (click for full images)


Excavations & Retaining Walls, April 2016 (click for full images)

לחצו לתמונות מוגדלות


Videos